2011 · Pipeline construction

Croatian transit DN 800 gas pipeline earthworks

2011 – Croatian transit DN 800 gas pipeline earthworks
2011 – Croatian transit DN 800 gas pipeline earthworks2011 – Croatian transit DN 800 gas pipeline earthworks
Project page online
Length
206 km
Duration
16 months
Year
2011

About the project

Substructure and complete earthworks for the Városföld–Bátmonostor–Drávaszerdahely DN 800 gas pipeline, with sheet pile support and groundwater lowering using wellpoints and open pumping.

Operations Pipeline construction