2007 · Earthworks and civil engineering
Hankook tyre factory, phase II
Shaping earthworks for phase II.
- Volume
- 600,000 m³
- Duration
- 4 months
- Year
- 2007
- Photographs
- 2
01 · Overview
About the project
Shaping earthworks for phase II. 600,000 m³. Duration: 4 months.
Operations on this project
02 · Photographs
From the site

Group
Go to t-trimmer.hu (opens in a new tab)Our sister company T-Trimmer handles machine sales, hire and parts.
Enquiries
Planning similar work?
Describe the location, the task and the planned schedule.
Plant yard